The long-awaited four-lane elevated corridor along East Coast Road (ECR) from Thiruvanmiyur to Uthandi is likely to face more delays. State Highways Minister Aadhav Arjuna has suggested canceling the project, even though a tender was finalized and work was assigned.
The 13.4-km project was awarded to a construction company, which prepared for work by mobilizing workers and machinery and conducting soil tests. However, on November 13, Mr. Arjuna told reporters that the project had been sent to a government team and would be canceled because the tender was given before land acquisition was completed.
Official sources said the company informed Tamil Nadu Highways State Authority on October 12 that 90% of the required land for construction had already been acquired, which should be enough to start work. Additional land needs for features like ramps wouldn’t delay the project’s start.
The four-lane elevated road is being built under a public-private partnership model, where the state contributes 40% of the cost and the contractor covers the rest. The project aims to reduce traffic congestion on ECR, which has 17 traffic signals in just 14 km, leading to frequent slowdowns.
The average distance between signals is about 0.82 km, causing heavy traffic jams as vehicles follow each other without space to overtake. There are also 347 crossroads along the route, adding to congestion. The elevated corridor was designed to ease traffic at key points like Lattice Bridge Road and Akkarai.
If a new tender is issued, the cost would rise by at least 20% due to inflation over the last two years. A retired highways engineer warned that legal battles between the contractor and government could further delay the project.
Similar delays have happened before. After the Tamilaga Vettri Kazhagam came to power, they canceled the Oragadam–Cheyyar Industrial Corridor Road Project, which aimed to improve connectivity for industries. Tenders for part of the Chennai Peripheral Ring Road were also canceled due to administrative issues.
There is no clear reason for these cancellations or when new tenders might be issued. The delays highlight ongoing challenges in infrastructure projects across the state.