Residents in Ganesapuram have called on the Greater Chennai Corporation (GCC) and Railways to speed up work on a much-awaited flyover that has been delayed for years. They are also filing RTI applications to find out why the project is taking so long.
V. Anand, one of the residents, mentioned that during the northeast monsoon season, the current subway used by drivers is unsafe. This is because the flyover project remains unfinished despite being promised for completion. Another resident, S. Venkatesan, pointed out how traffic jams have become a major problem in the area.
S.S. Sharavana Kumar, who lives near Vyasarpadi, said construction of the flyover started in January 2023 and was supposed to finish by early 2025. However, nearly four years later, it is still incomplete. This has caused ongoing traffic issues and hurt local businesses. Despite many requests to higher officials, no progress has been made.
Residents shared a recent response from the Chief Minister’s Cell, which stated that 75% of the flyover’s work was completed, with 11 out of 15 sections built. The remaining sections are waiting for Railways’ approval to continue construction. GCC also said it would take another five months to finish the project.
A response from the Prime Minister’s Office mentioned that a plan for the flyover was sent to Railways in October but has not been approved yet. Without this approval, the project cannot move forward.
Residents are frustrated because the delay has lasted nearly four years, and they feel stuck with no end in sight. They believe that waiting for Railways’ approval is not enough of a reason for such delays. They urged GCC to take stronger steps to push for progress and set clear deadlines.
The residents have asked the Corporation Commissioner to get involved and ensure the project moves forward quickly. They also want a senior official to work closely with Railways until the project resumes and completes.
Meanwhile, all other pending projects should be sped up as well, they added.